Reporting: Growing Business Fund
RW resented the reports noting that the GBF was funded from the Growth Deal where funds had to be
spent by 31st March 2022 so the focus was on paying outstanding grants to minimise the level unpaid
which will be clawed back by Government.
AP asked if project costs were being impacted by inflation. RW confirmed that some GPF requests had
been received but not for the GBF as, if costs rise, it usually results in a lower intervention rate. RW
agreed to investigate this further.
The Committee agreed:
• To note the content of the report
Growing Places Fund Programme Project RAG ratings - Confidential
The GPF RAG ratings were taken as included in the meeting papers.
The Committee agreed:
• To note the content of the report
Growing Places Fund: FEP Energy project update Confidential
Getting Building Fund: Local Full Fibre Network project amendment request
JR presented the project which is part of the wider Better Broadband project and advised that 14 sites have
needed to be withdrawn reducing the project costs by £400k. To avoid having to repay this the project
team have proposed using the funding to provide Fixed Wireless Access to a number of sites which will
provide the same outcomes to rural areas which traditional broadband is struggling to reach.
The Committee agreed:
• To note the content of the report
• To approve the deallocation of £400,000 from the Getting Building Fund grant offer of £2,054,320 for
the delivery of the Local Full Fibre Network. To re-apportioned the £400,000 within the project to
support the delivery of Fixed Wireless Access
Suffolk Inclusive Growth Investment Fund - Round 5 projects for approval - Confidential